Client : PetroChina International Jabung Ltd.
Year : 2016
Status : Finished
Scope of Work :
Front End Engineering Design (FEED) for a 3 km underground gas pipeline with a 6-inch pipe and a 3 km gas pipeline with a 4-inch pipe. In order to minimize the disturbance to the environment, both pipelines are designed to suit the horizontal directional drilling (HDD) approach at river crossings and road crossings. Pig launcher and receiver are also installed for pipeline pigging purposes.