Client : Joint Operating Body Pertamina - Talisman Jambi Merang (JOB PTJM) & PetroChina International Jabung Ltd.
Year : 2014-2015
Status : Finished
Scope of Work :
Detailed engineering for brownfield plant for new condensate storage tank facilities installation with main equipment used in the project are as follows:
- Two storage tanks with 6,000 bbl and 20,000 bbl capacity
- Condensate pump
- Custody meter
- Vent stack
- Utilities such as instrument air system and firewater system
Related Projects

Engineering, Procurement, Construction, and Installation (EPCI) | Jabung in Jambi, Sumatra
EPCI for Fire Fighting System Upgrade WB & SWB PPF

Engineering, Procurement, Construction, and Installation (EPCI) | West Madura, East Java
EPCI for PHE KE-38 W ellhead Platform (WHP) Modification

Engineering, Procurement, Construction, and Installation (EPCI) | Sengkang, South Sulawesi
EPCI for Kampung Baru Gas Plant Train # 2

Engineering, Procurement, Construction, and Installation (EPCI) | Jabung, Jambi
EPCI for Upgrading Fire Fighting System WB & SWB PPF

Engineering, Procurement, Construction, and Installation (EPCI) | Sengkang, South Sulawesi
EPCI for Patila Metering Station

Engineering, Procurement, Construction, and Installation (EPCI) | Payo Selincah in Jambi, Sumatra