Client : BP BERAU LTD. & PT BINA SARANA PUTRA
Period : 2023
Scope of Work:
Providing Detailed Engineering Design (DED) for company with following scope of work:
- Construct flowline to connect each Xmas tree wing valve to existing VRB production manifold with single flowline configuration for each well (no comingle).
- Complete each flowline with its accessories such as wet gas flow meters, choke valve, non-intrusive sand detector, sampling point, and through conduit double expanding gate
Connect the wells to VRB WHCP system.