Client : PT Perusahaan Listrik Negara (PLN)
Year : 2011
Status : Finished
Scope of Work :
Detailed engineering for fuel gas receiving station in Payo Selincah Power Plant that has a capacity of 30 MMscfd to supply the 100MW gas turbine generator. The main equipment used for the project are as follows:
- Fuel Gas Scrubber
- Fuel Gas Filter
- Custody Meter
- Pipeline
- Utilities (Instrument Air System, Firewater System, Power System, and Vent System)